Rosedale Valley Road: What to Expect in 2027

By Sheppard (Şiwan) Akpinar, BENA representative to the Midtown Ravines Group

The Rosedale Valley Road multi-use trail is set for a significant upgrade, but the construction schedule still depends on funding approval. At BENA’s November 4 annual general meeting, City of Toronto Senior Project Manager Pranav Bhajiwala outlined the plans for the trail between Bayview Avenue and Park Road.

Why the trail needs attention

The existing route has narrow sections, steep changes in grade, damaged surfaces, erosion and little separation from passing vehicles. It also lacks lighting, making it less welcoming during darker hours. The redesign aims to improve everyday use for people walking, cycling, pushing strollers or using mobility devices.

The proposed trail will be three metres wide, with 0.6-metre buffers on either side. A 1.5-metre separation from the road is planned where space permits, with at least 0.8 metres in tighter sections. Gentler grades, resting areas, and improved trail entrances are also planned, including seating and bike parking at Park Road.

Care for the ravine

Because the route passes through an ecologically sensitive valley, the City has worked with the Toronto and Region Conservation Authority. Pranav said trees will need to be removed, with each removed tree to be replaced using native species under the City’s ravine guidelines. He did not provide a tree count.

New lighting is planned along the path, with fixtures directed toward the trail rather than the road or surrounding habitat. A bat survey informed the design. Licensed archaeologists and environmental consultants will be present during construction to ensure the contractor meets the relevant archaeological and environmental requirements.

Two people walk along a leaf-strewn path beside a road through a wooded area.


Timing and access

The City submitted its funding request at the end of October and, as of the November 4 meeting, expected an answer during November. Approval had not yet been confirmed. Subject to that approval, tendering was anticipated from November through January, with a contractor expected in February. Tree removal is planned for mid-February through March 31, with March 31 identified as a firm deadline ahead of bird breeding
season. Construction would begin in spring 2027 and take roughly eight months.

During active work, sections of the trail will close, with detours posted and off-peak road-lane restrictions anticipated. The City has asked community groups to flag public events so access and construction closures can be coordinated where possible. We will share further information as the City confirms the schedule.

Background information and project updates can be found at the City’s Rosedale Valley Road Multi-Use Trail Reconstruction web page.